Weekly Report for May 21st 2025.

Overall Status
On Track
Low Risk
High Risk
Deferred
Completed
Summary

Completed team onboarding and resource planning; key risk remains onboarding the Creative Director, with next steps focused on communicating the design system plan and advancing project milestones.

Activities completed last week 🎉
Onboarded Design Manager on 5/19 to support AccessNS, IMAU and TYES
Onboarded Sr UI Designers (Mike and Brandon) to design system
Activities planned for this week 🎯
Onboarded Design Manager on 5/19 to support AccessNS, IMAU and TYES
Process alignment across design and project teams, with a focus on Jira and task tracking
Begin weekly resource/project planning syncs (kickoff check-in with Jose)
Project Activities/Milestones  🗓️
Fully onboard team. Risk/Dependencies: Creative Director onboarding targeting for early June
CrewPro - Supply Source Web App
Design System - Setting the color palette
Heartbeat - Refine the Map View functionality
MTR - Cleaning up the training prototype
UX CoE - Define design processes
Delivery Lead
Design Manager
David Forgash
Project Manager
Ketaki Sontakke
Client Sponsor
Eileen Relford
Client Lead
Jose Martinez
Reporting Period
May 21, 2025